Demo

Try ProjectCAPEX with example programmes

This is the real ProjectCAPEX app, loaded with five example programmes. You get your own copy, so you can change anything you like, and your copy is deleted after 7 days. The programmes, companies and people in it are fictional.

A laptop and a phone showing programme status dashboards on a desk by a window, with a city waterfront behind.

Pick a role

You sign in with that role’s permissions. You can switch role from the demo bar at any time.

  • Executive Sponsor

    Is it on track, what will it cost, and what do I need to decide?

    Views everything and approves decisions, change requests and gates, but changes nothing else.

    Start the demo
  • Programme Manager

    Plan progress, RAID, overdue actions and the next milestones on the critical path.

    Edits the plan, RAID, budget, quality gates and reports.

    Start the demo
  • Head of IT

    Interfaces, environments, data loads, security roles and technical defects.

    Edits delivery work on the programmes.

    Start the demo
  • Business Head

    Will my teams be ready: training, UAT, change impact, key users and sign-offs.

    Edits delivery work on the programmes.

    Start the demo
  • PMO Lead

    All five programmes at once: health, variance, quality gates, people and lessons.

    Sees the whole portfolio, with every permission.

    Start the demo
  • Test and Cutover Manager

    Test cycles, the defect burn-down, the cutover runbook and the go / no-go checklist.

    Lands on the SAP programme’s testing and cutover. Edits tests, defects and RAID.

    Start the demo
  • Data Migration Lead

    Migration objects, load cycles, rejected records and the data risks before cutover.

    Edits data migration and RAID on the programmes.

    Start the demo
  • Training Lead

    Courses, sessions and completion by role, so every user is ready on day one.

    Edits training and RAID on the programmes.

    Start the demo

What each role sees

A preview of the dashboards each role works from. Pick a seat and a programme.

Choose a seat
Choose a programme

Executive Sponsor

SAP S/4HANA greenfield

Build is on plan, but mock load 2 rejected too many business partner and open item records, so data migration is the risk to go-live.

Company
Halden Precision Group
Phase
Realize
Go-live
6 Apr 2027
Health
At risk

Is it on track, what will it cost, and what do I need to decide?

Budget at completion€14.2MForecast €14.6M
Spent to date€6.94M49% of budget
Days to go-live165 daysGo-live 6 Apr 2027
Plan complete46%Realize, sprint 5 of 8

Overall status

At risk
  • Data migration, off track. Mock load 2 rejected 6.8% of business partner records against a 2% target.
  • Schedule, at risk. Mock load 3 moved one week; float to the dress rehearsal is now 9 days.
  • Budget, at risk. Forecast €0.4M over, driven by data cleansing contractors.
  • Build, on track. 142 of 188 WRICEF objects through unit test, on plan.
From the RAG summary

Go-live confidence

At risk

-6 points this week. Down after mock load 2: two data objects are above their error threshold.

From go-live gate criteria

Budget, actual against plan

€6.94M spent, €290K over plan in Oct. Forecast €14.6M of €14.2M.

  • Plan
  • Actual
From Budget and cost entries

Top 3 risks

  1. 20Business partner duplicates block mock load 3 sign-offRSK-041, owner Ines VogelRising
  2. 16Open item reconciliation for 3 company codes not agreedRSK-037, owner Tomas BergSteady
  3. 12EDI partner testing window overlaps plant shutdownRSK-029, owner Priya RamanFalling
From the Risks register

Decisions needed from me

2
  • Due30 OctApprove two extra data cleansing contractors until mock load 3DEC-058. If it slips: mock load 3 slips a further week.
  • Due6 NovArchive vendors with no activity since 2021 instead of migrating themDEC-061. If it slips: 38,000 extra records to cleanse.
From the Decisions log

Milestone timeline

  1. Explore exitJun 2026Done
  2. Mock load 2Oct 2026Done
  3. Realize exitDec 2026In progress
  4. Mock load 3Jan 2027Late
  5. Dress rehearsalMar 2027Upcoming
  6. Go-live6 Apr 2027Upcoming
From Milestones in the plan

Run your own programme this way

Bring your plan, RAID log and runbook. Every view on this page comes from records you already keep.